MTI programmes implemented by the NDC have a vital role to play in developing the SME sector efficiently and effectively by means of setting appropriate Policy and Programme, availing land for development of businesses, creating an enabling infrastructure for lease at affordable rental rates, setting Best Practice Model for SME Business to grow and to flourish with key outputs job creation and growing the economy

Karas Region

Keetmanshoop Community Market (! Homs Ai)

Activities undertaken
Land located in Kronlein-Tseiblaagte for this project was acquired from the Keetmanshoop Town Council (KTC). The concept designs and technical documentation commenced, and discussed with KTC while the three dimensional designs and project name were submitted to the Ministry for approval.

Employment Creation
During Construction: 107 persons
During business operation: 78 persons anticipated

Budget
Projected MTI Investment: N$14 million

Karasburg Community Market

Activities undertaken
Kalkfontein Hotel has been earmarked by the NDC, Project Technical Team and Karasburg Town Council respectively to be acquired for this project due to its strategic locality, capacity to serve as a tool for integrating various communities and its potential to serve this purpose.

Project construction to commence during April-May 2012.

Employment Creation (Projected)
During Construction: 131
During Business Operations: 92

Budget
Projected MTI Investment: N$13 million

Noordoewer Community Market

Activities undertaken
A strategically located site alongside Main Road B1 has been earmarked by the NDC, Project Technical Team and Karas Regional Council respectively to be acquired for this project.
A site inspection was undertaken by the technical team, enabling the technical team to commence with site survey and Project Design Development.

Employment Creation (projected)
During Construction: 131
During Business Operations: 68

Budget
Projected MTI Investment: N$14 million

Gainachas Community Market

Activities undertaken
A strategically located site in the centre of Gainachas has been earmarked by the NDC, Project Technical Team and Gainachas Development Committee respectively to be acquired for this project.

Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Employment Creation (projected)
During Construction: 58
During Business Operations: 30

Budget
Projected MTI Investment: N$5 million

Berseba Community Market

Activities undertaken
A site strategically located in the centre of Berseba has been earmarked by the NDC, Project Technical Team and Berseba Village Council respectively to be acquired for this project.
A site inspection was undertaken by the technical team, enabling the technical team to commence with site survey and Project Design Development.

Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Employment Creation (projected)
During Construction: 120
During Business Operations: 75

Budget
Projected MTI Investment: N$15 million

Hardap Region

Gibeon Community Market

Activities undertaken
A site located strategically at the fountain of Gibeon adjacent the main road passing alongside Gibeon has been earmarked by the NDC, Project Technical Team and Gibeon Village Council respectively to be acquired for this project.

Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Employment Creation (projected)
During Construction: 120
During Business Operations: 75

Gochas Community Market

Activities undertaken
A strategically located site at the entrance to Gochas has been earmarked by the NDC, Project Technical Team and Gochas Village Council respectively to be acquired for this project.

Employment Creation (projected)
During Construction: 120
During Business Operations: 75

Budget
Projected MTI Investment: N$14 million

Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Mariental Trade & Industrial Estate

Activities undertaken
A strategically located site approximately 15ha site in the none flood area of Mariental has been earmarked by the NDC, Project Technical Team and Mariental Town Council respectively to be acquired for this project due to its strategic locality, size and potential to contribute to integration of the various communities of Mariental towards one.

Employment Creation (projected)
During Construction: 980
During Business Operations: 375

Budget

Projected MTI Investment: N$45 million
Khomas Region

Windhoek Garment Factory (Tuhafeni)

Activities Undertaken
The strategically located land for this project was acquired from the City of Windhoek at a cost of N$ 4 245 400 million. This site is located in the Northern Industrial Zone close to Namibia Broadcasting Corporation TV complex. The concept designs and technical documentation commenced, completed and three dimensional designs and name approved by the Ministry.
Tenders were call.

Work is in progress is on schedule.

The practical completion date for the factory is 10 March 2012.

A corporate identity logo and slogan has been developed and is ready to be presented by NDC to the Ministry for input and approval.

Recruitment of an operator for this factory is underway.

Employment Creation (projected)
During Construction: 211
During Business Operations: 450

Budget
Projected MTI Investment: N$28 million

Erongo Region

Walvis Bay Industrial Estate (! Nara Namib)

This Estate has been earmarked to be serving as Logistical, assembling and manufacturing node with downstream businesses such as welding, packaging, etc.

Activities undertaken
The Walvis Bay Town Council has allocated eighteen hectare of land to the Ministry for this initiative. The preparation of technical documentation for the infrastructure services such as water, sewer, electricity, roads and storm water handling commenced and is in progress.

Construction tender for phase 1 of the project shall be called 30 September 2011 and construction work on site is scheduled to commence mid January 2012.

Employment Creation (projected)
During Construction: 1200
During Business Operations: 1000 direct jobs plus 10000 downstream jobs

Budget
Projected MTI Investment: N$300 million

Omaruru Trade & Industrial Estate

Activities undertaken
A strategically located site measuring approximately 16ha has been earmarked by the NDC, Project Technical Team and Omaruru Town Council respectively to be acquired for this project due to its strategic locality towards entrance to town from Karibib, size and potential to contribute to integration of the various communities of Omaruru towards one.

Construction tenders shall be called during March 2012 whilst construction of the Phase one (Events Centre – Trade Fair Facility) shall commence April-May 2012.

Employment Creation (projected)
During Construction: 980
During Business Operations: 375

Budget

Projected MTI Investment: N$140.6 million phased development
Kunene Region

Outjo Community Market

Activities undertaken
A strategically located site in the centre of Outjo has been earmarked by the NDC, Project Technical Team and Outjo Town Council respectively to be acquired for this project.

Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Employment Creation (projected)
During Construction: 76
During Business Operations: 40

Budget
Projected MTI Investment: N$10.6 million

Otjozondjupa Region

Kalkfeld Community Market

Activities undertaken
A strategically located site in the centre of Kalkfeld adjacent the main road has been earmarked by the NDC, Project Technical Team and Kalkfeld Settlement Council respectively to be acquired for this project.

Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Employment Creation (projected)
During Construction: 76
During Business Operations: 40

Budget
Projected MTI Investment: N$7.6 million

Grootfontein SME Industrial Park

Activities undertaken
A strategically located site in the centre of the Industrial Area has been earmarked by the NDC, Project Technical Team and Grootfontein Town Council respectively to be acquired for this project due to its strategic locality and potential to serve this purpose.

Compiling of technical documentation is underway and Construction tenders shall be called during March 2012 whilst construction of the market shall commence April-May 2012.

Employment Creation (projected)
During Construction: 76
During Business Operations: 40

Budget
Projected MTI Investment: N$20 million

Okahandja Craft Market

Activities undertaken
The site to the entrance of town, where crafts entrepreneurs are currently operating, has been earmarked by the NDC, Project Technical Team and Okahandja Town Council respectively to be retained for this project due to its strategic locality, historic marketing, choice of the beneficiaries and potential to serve this purpose.

Construction tenders shall be called during April 2012 whilst construction of the market shall commence May-June 2012.

Employment Creation (projected)
During Construction: 98
During Business Operations: 120

Budget
Projected MTI Investment: N$13.11 million

Okahandja Business Estate (Omumbonde)

Background information
A strategically located site on the high way en route from Windhoek to Swakopmund measuring approximately five hectare was secured from Ministry of Works.

Activities undertaken
The land for this project was acquired. The concept designs and technical documentation commenced, completed and three dimensional designs approved by the Ministry.

Construction tenders for Phase 2 shall be called during November 2011 whilst construction of the industrial workshops shall commence mid January 2012.

Employment Creation (projected)
During Construction: 150
During Business Operations: 420

Budget
Projected MTI Investment: N$150 million

Kavango Region

Kavango Trade and Industrial Estate

An application was lodged to Rundu Town Council for the avalanche of a six hectare site to MTI and for its Title Deed to be registered with NDC. Rundu Municipality granted NDC permission to access the site for construction purposes and RTC did not yet resolved on the application submitted to them to avail the by them identified site to MTI/NDC. Feed back is being awaited.

Activities undertaken
The concept design in 3-D Graphic format has been discussed and approved by the Rundu Town Council, Kavango Regional Council and other local stakeholders. The concept design in the form of a three dimensional design has been submitted to the Ministry for endorsement.
.
Employment Creation (projected)
During Construction: 170
During Business Operations: 420

Budget
Projected MTI Investment: N$210 million

Kaprivi Region

Katima Mulilo Trade and Industrial Estate

Activities undertaken
The concept design in 3-D Graphic format has been discussed and approved by the Katima Town Council, Caprivi Regional Council and other local stakeholders. The concept design in the form of a three dimensional design has been submitted to the Ministry for endorsement.

The technical documentation pertaining a phased development commenced with phase 1 documentation completed.

Construction Tenders for phase one is currently running and work on phase one should commence by mid November 2011

Employment Creation (projected)
During Construction: 170
During Business Operations: 420

Budget
Projected MTI Investment: N$210 million

Oshikoto Region

Tsumeb Community Market (Sida! Hanab)

Activities undertaken
The strategically located land for this project was acquired from the Tsumeb Town Council (TTC). The concept designs and technical documentation commenced, and discussed with TTC while the three dimensional designs were submitted to the Ministry for approval.

The contractor is on site for the construction of the market. Work is in progress.

The practical completion date for the market is 15 February 2012.

Employment Creation
During Construction: 107
During Business Operations: 78 (projected)

Budget
Projected MTI Investment: N$11 million

Tsumeb Trade & Industrial Estate

Activities undertaken
Strategically located site measuring approximately 20ha has been earmarked by the NDC, Project Technical Team, Regional Councillor and Tsumeb Town Council respectively to be acquired for this project due to its strategic locality in terms of visibility, accessibility, location regarding urban hub establishment in relation to the Tsumeb-Katwitwi high way, size and potential to contribute to integration of the various communities of Tsumeb towards one.

Upon completion of the 3-D Graphic Design, such design shall be presented to the Tsumeb Town Council and to MTI for input and approval upon which NDC shall proceed with compiling technical documentation.

Due to the site not yet been acquired, design development has not commenced.

Employment Creation (projected)
During Construction: 980
During Business Operations: 375

Budget
Projected MTI Investment: N$140.6 million phased development

MTI Oshikoto Regional Office and SME Park Expansion at Omuthiya

Activities undertaken
The land for the site is part of the current SME Park which is strategically located along the main road passing through Omuthiya. The concept designs and technical documentation commenced, completed and three dimensional designs approved by the Ministry.

Tenders were called.

The contractor is on site for the construction of the facility. Work is in progress.

The practical completion date for the facility is end February 2012.

Employment Creation (projected)
During Construction: 98
During Business Operations: 36 (projected)

Budget
Projected MTI Investment: N$11.4 million phased development

Onethindi-Ondangwa Community Market (Okutopola)

Activities undertaken
The strategically located land for this project was acquired from the Oshikoto Regional Council (ORC). The concept designs and technical documentation commenced, and discussed with ORC while the three dimensional designs were submitted to the Ministry for approval.

The contractor is on site for the construction of the market. Work is in progress.

The practical completion date for the market is scheduled for March 2012.

Employment Creation (projected)
During Construction: 107
During Business Operations: 78 (projected)

Budget
Projected MTI Investment: N$12 million phased development

Oshivello Community Market

Activities undertaken
A strategically located site in Oshivello adjacent the main road and service station, gateway to the North, has been allocated by the Oshikoto Regional Council to MTI/NDC for this project due to its strategic locality and potential to serve its purpose.

Construction Tenders is scheduled to be called for during March 2012 whilst construction work should commence by start of June 2012.

Employment Creation (projected)
During Construction: 76
During Business Operations: 40

Budget
Projected MTI Investment: N$14.6 million

Onathinge Community Market

Activities undertaken
A strategically located site in Onathinge adjacent the main road has been allocated by the Oshikoto Regional Council to MTI/NDC for this project due to its strategic locality and potential to serve its purpose.

Onayena Community Market

Activities undertaken
A strategically located site at Onayena adjacent the main road and turn-off to Onayena has been allocated by the Oshikoto Regional Council to MTI/NDC for this project due to its strategic locality and potential to serve its purpose.

Construction Tenders is scheduled to be called for during March 2012 whilst construction work should commence by start of June 2012.

Employment Creation (projected)
During Construction: 76
During Business Operations: 40

Budget

Projected MTI Investment: N$14.6 million
Oshana Region

Oshakati Trade and Industrial Estate (OMUGONGO LIFESTYLE ESTATE)
(Oshakati Agro food Processing Centre)

Activities undertaken
The concept designs and technical documentation commenced, completed and three dimensional designs being endorsed by the Ministry. The concept designs were discussed with Oshakati mayor for inputs and approved by the Oshakti Town Council.

The practical completion date for the on-site services reticulation and infrastructure facility is September 2011.

Employment Creation
During Construction: 153
During Business Operations: 390 (projected)

Budget
Projected MTI Investment: N$300 million

Omusati Region

Ruacana Community Market (Twapandula)

Activities undertaken
The strategically located land for this project was acquired from the Ruacana Town Council (RTC). The concept designs and technical documentation commenced, and discussed with RTC while the three dimensional designs were submitted to the Ministry for approval.

The concept designs and technical documentation were completed and tenders were called.

The contractor is on site for the construction of the market. Work is in progress.

The practical completion date for the facility is 30 November 2011.

Employment Creation

During Construction: 107
During Business Operations: 78 (projected)

Budget
Projected MTI Investment: N$14 million

Ohangwena Region

Activities undertaken
A well located site has been identified by the NDC in collaboration with the Ohangwena Regional Council (ORC), which site was granted to the MTI/NDC during May 2011. The site survey was done upon which the project development planning and project concept design has commenced.

Construction Tenders is scheduled to be called for during April 2012 whilst construction work should commence by start of July 2012.

Employment Creation (projected)
During Construction: 107
During Business Operations: 78

Budget
Projected MTI Investment: N$39.4 million

Eenhana Business Park (phase 2) & MTI OHANGWENA REGIONAL OFFICES

Activities undertaken
A well located site belonging to the MTI/NDC shall be developed. The site was visited by the technical team for information gathering upon which the project development planning and project concept design will commence starting with a 3-D graphic design.

Tenders to be called during March 2012.

Employment Creation (projected)
During Construction: 107
During Business Operations: 78

Budget
Projected MTI Investment: N$55 million

 

 